How to put retainage in a cash flow forecast

By Michael Gardner Goodwin · November 11, 2026 · 4 min read

Short answer: give retainage its own line, on the week it is likely to be released after closeout. Retainage your customer holds is a receivable, not cash. Retainage you hold for subs is cash you owe.

Your 13 weeks, from your bank.

TreasuryFlow builds the 13-week forecast from your bank history. $299/mo per company.

What retainage is

Retainage is the part of each progress payment the owner holds back until the work is done. The contract sets the rate and when it is released.

On federal fixed-price construction, FAR 52.232-5 lets the contracting officer hold back up to 10 percent of a payment when progress is not satisfactory. Private and state contracts set their own terms.

Two sides: what you are owed and what you owe

Retainage in a 13-week forecast.
LineTreat it as
Retainage your customer holdsA late receivable, on the week it is likely to be released after closeout
Retainage you hold from subsCash you owe, on the week you release it
Retention you keep in its own bank accountRestricted cash, not spendable

One job, worked

Example figures for one job: a $1,500,000 contract, 80% complete, $1,200,000 billed. Subs have billed $450,000. Not a real business.
Retainage on this jobAmount
Your customer holds 10% of $1,200,000$120,000
You hold 10% of $450,000 from subs−$45,000
Net retainage owed to you$75,000

Say the contract releases retainage 60 days after closeout and your subs are paid when you are. The forecast shows $120,000 in and $45,000 out in the same week, 60 days after the job closes.

If closeout slips a month, both lines move a month.

Why it comes back late

Put retainage on the week you realistically expect it, and move it every time the job slips.

Keep retention you hold out of spendable cash

Retention held for subs is not yours to spend. If it sits in its own bank account, keep that balance off the number you use to make payroll.

What TreasuryFlow does

Frequently asked questions

Is retainage receivable cash?

No. Your customer is still holding it. Count it as cash when it lands in the bank.

When should retainage go in a 13-week forecast?

On the week it is likely to be released after closeout, as its own line. Move it every time the job slips.

How much retainage can be held?

It depends on the contract. On federal fixed-price construction, FAR 52.232-5 allows up to 10 percent of a payment when progress is not satisfactory. Private and state contracts set their own terms.

How do I keep retention I hold for subs out of my cash number?

Keep it at a separate bank. In TreasuryFlow, tag that bank as escrow and its balance sits on a restricted line, outside spendable cash.

See your own lowest week.

Connect your bank and see the next 13 weeks.

Source: FAR 52.232-5, payments under fixed-price construction contracts, paragraph (e), via Cornell Legal Information Institute, read November 11, 2026.