How to put retainage in a cash flow forecast
Short answer: give retainage its own line, on the week it is likely to be released after closeout. Retainage your customer holds is a receivable, not cash. Retainage you hold for subs is cash you owe.
Your 13 weeks, from your bank.
TreasuryFlow builds the 13-week forecast from your bank history. $299/mo per company.
What retainage is
Retainage is the part of each progress payment the owner holds back until the work is done. The contract sets the rate and when it is released.
On federal fixed-price construction, FAR 52.232-5 lets the contracting officer hold back up to 10 percent of a payment when progress is not satisfactory. Private and state contracts set their own terms.
Two sides: what you are owed and what you owe
| Line | Treat it as |
|---|---|
| Retainage your customer holds | A late receivable, on the week it is likely to be released after closeout |
| Retainage you hold from subs | Cash you owe, on the week you release it |
| Retention you keep in its own bank account | Restricted cash, not spendable |
One job, worked
| Retainage on this job | Amount |
|---|---|
| Your customer holds 10% of $1,200,000 | $120,000 |
| You hold 10% of $450,000 from subs | −$45,000 |
| Net retainage owed to you | $75,000 |
Say the contract releases retainage 60 days after closeout and your subs are paid when you are. The forecast shows $120,000 in and $45,000 out in the same week, 60 days after the job closes.
If closeout slips a month, both lines move a month.
Why it comes back late
- The punch list and final inspection.
- Closeout paperwork, such as lien waivers and warranties.
- The owner's own approval cycle.
Put retainage on the week you realistically expect it, and move it every time the job slips.
Keep retention you hold out of spendable cash
Retention held for subs is not yours to spend. If it sits in its own bank account, keep that balance off the number you use to make payroll.
What TreasuryFlow does
- Its cash number comes from your bank balances, so retainage counts the day it lands, not the day it is billed.
- It builds the 13-week forecast from your bank history, starting from spendable cash. The payroll you confirm is checked against your cash and listed under the forecast.
- Keep retention at a separate bank? Tag that bank as escrow. Its balance moves to a restricted line, out of spendable cash and out of the forecast's starting balance.
Frequently asked questions
Is retainage receivable cash?
No. Your customer is still holding it. Count it as cash when it lands in the bank.
When should retainage go in a 13-week forecast?
On the week it is likely to be released after closeout, as its own line. Move it every time the job slips.
How much retainage can be held?
It depends on the contract. On federal fixed-price construction, FAR 52.232-5 allows up to 10 percent of a payment when progress is not satisfactory. Private and state contracts set their own terms.
How do I keep retention I hold for subs out of my cash number?
Keep it at a separate bank. In TreasuryFlow, tag that bank as escrow and its balance sits on a restricted line, outside spendable cash.
Source: FAR 52.232-5, payments under fixed-price construction contracts, paragraph (e), via Cornell Legal Information Institute, read November 11, 2026.