Underbilling and overbilling: what your WIP says about cash

By Michael Gardner Goodwin · November 11, 2026 · 4 min read

Short answer: underbilling is work you have earned but not billed, so nobody has been asked for that cash. Overbilling is billing ahead of the work, so you hold cash the job still needs. Both show on a work-in-progress schedule.

See what reached the bank.

TreasuryFlow adds your banks into one cash number and builds a 13-week forecast from your bank history. $299/mo per company.

How to calculate it

  1. Percent complete: cost to date divided by total estimated cost.
  2. Earned revenue: percent complete times the contract value.
  3. Compare earned revenue with billed to date. Earned more than billed is underbilled. Billed more than earned is overbilled.

This is the cost-to-cost method, the usual way contractors measure percent complete.

Three jobs, worked

Example figures. Percent complete is cost to date over estimated cost. Not a real business.
JobContractCompleteEarned
Job A$1,200,00060%$720,000
Job B$800,00025%$200,000
Job C$450,00090%$405,000
Example figures, continued: earned against billed.
JobEarnedBilledOver or under
Job A$720,000$640,000Under $80,000
Job B$200,000$260,000Over $60,000
Job C$405,000$405,000Even
All three$1,325,000$1,305,000Under $20,000

The net hides both stories. Job A has $80,000 of finished work nobody has been asked to pay for. Job B is holding $60,000 its remaining work still needs.

What underbilling does to cash

Underbilled work is on no invoice, so it is in no receivable and on no forecast. Until you bill it, it cannot arrive.

A CPA firm's guide warns that growing underbillings can leave you financing the job, and can point to unapproved change orders or profit erosion not yet recognized.

What overbilling does to cash

Overbilled cash is in the bank, but the job still owes the work. On the balance sheet it is a liability: billings in excess of costs and estimated earnings.

Spend it elsewhere and the account runs short when the job's costs arrive.

Read it weekly, not at month end

A schedule built at close is a month late. Update percent complete on the largest jobs each week, and bill underbilled work before the next pay date.

What TreasuryFlow does

Frequently asked questions

What is underbilling in construction?

Work you have earned but not yet billed. On a WIP schedule it is earned revenue above billings to date, and it shows as an asset: costs and estimated earnings in excess of billings.

What is overbilling?

Billing ahead of the work. It is billings above earned revenue, and it shows as a liability: billings in excess of costs and estimated earnings.

Is overbilling good for cash flow?

It puts cash in the bank early, but the job still owes the work. Keep that cash for the job's remaining costs.

How is percent complete calculated?

Usually cost to cost: cost to date divided by total estimated cost. Earned revenue is that percentage of the contract value.